gapilot vans RV7 quick build kit
My Great Lakes 2T-1A-2 Rebuild Diary 2007.

27/28/29-December-2007. While waiting for some parts to arrive I had a look at the R/H upper wing. It has been inspected by my inspector and the spars are okay. The wing just needs some small items replaced and refurbished. Cleaned and revarnish.
I also decided to fit the L/H upper wing to the centre section. I had removed the inner rib and I want to ensure it alignes with the centre section properly.


R/H Upper wing just needs a little work.
Small items (on the R/H Wing) like the joint on this inspection hole needed to be repaired.
Back to the L/H Upper wing. Fixing the centre wooden brace..
Applied some varnish.
Checking the alignment for the L/H upper wing connection to centre section.
I needed to replace the blocks at the top and bottom of the spar, this effects the position of the inner rib so I fitted the wing to the centre section to make sure the alignment is correct.
Looks good to me!
Trailing edge is in alignment.
Leading edge looks good.
  Copyright © 2007, 2008 GreatLakes2T .co.uk All rights reserved. All pictures are property of GreatLakes2T (unless noted) please do not reproduce. For more information contact webmaster [at] greatlakes2t .co.uk This site is NOT the official Great Lakes Inc site. The contents of this site are the opinion of the author, not PFA, FAA or CAA. Please check all information is correct before you act upon it.